- Business and Development
- Utility Bills
- Regional Parks
- Roads
- Business License
- Traffic Concerns
- Utility Bills
- Engineering & Capital Projects
- Development Services
- Capital Projects
- Environmental
- Sewer and Reclaim Water Utilities
- Traffic and Roads
- Drainage and Flooding
- Know Your Flood Risk
- Take Action
- Severe Weather Info
- Emergency Management
- Water Monitoring and Response
- Grading Permits
- Federal Flood and Insurance Programs
- Planning
- Boards, Commissions & Committees
- Equipment Services, Facilities and Roads
Project Timeline
Initial Efforts
- 2021: Project Initiated in 2021
- Winter and Summer 2024: Submission and technical review completed with the Federal Emergency Management Agency (FEMA)
We Are Here: Current Status
- Winter 2025: Community Engagement and Public Comment Period
Next Steps
- Summer 2025: FEMA Issuance of Determination Letter
- Spring/Summer 2025: 90-day Technical Appeal Period
- Summer 2025: Updated Insurance Requirements & FEMA Mapping Effective
Downloadable Timeline Available